|
Plant
brings power to the people
Keeping a
campus like Caltech running calls for electricity, and lots of it. We
require a plentiful and reliable source of alternating current to run
our computers, light our workspace, and keep us comfortable. Our energy
needs are a potential weakness, as demonstrated during the power crisis
of 2001. One of the tough lessons that Caltech learned at that time is
that the campus would be better off if it produced at least as much power
as it consumes.
One of several
ambitious projects designed to cut Caltechs reliance on outside
sources of energy will replace aging turbines with new, more powerful
ones. Since November, workers have been busily gutting Central Plant of
its old cogeneration system, the large jet aircraft engine that provided
the campus with its electrical power.
Once completed,
the new and improved Central Plant will generate approximately 80 percent
of the power that the Institute needs. But the job is complex.
It
is very difficult because our business is continuous: you have to provide
utilities to the campus at all times, says Reza Ohadi, the director
of campus operations. To stay in business and do the retrofit is
very tough. Thank God, we have a good team.
This 130-person
team is a collection of mechanics, engineers, electricians, system analysts,
and all manner of tradespeople. Relying on their labor and expertise has
provided Ohadi with the means of avoiding the greater costs associated
with major construction projects like this one.
To
perform as cost-effectively as possible, we are not using a general contractor;
we are the general contractor, he says. We are doing much
of the cogen installation ourselves. We hire the expertise
and use subcontractors as needed.
Looking back
on the progress that has been made, and considering the quality of work
that his men are performing, Ohadi predicts success. I think this
project is going to be unique and the work will be of outstanding quality.
Considering
the size of the operation, its $10 million dollar budget is quite lean.
But because they are doing much of the work in-house, Central Plant is
saving between $5 and $10 million.
The retrofit
consists of removing a steam turbine and a natural gas turbine, massive
hulks that produced 4.5 megawatts of power. The system worked perfectly,
but it filled only about 40 percent of the Institutes hourly electricity
needs. The remainder of the Institutes power was purchased from
the city of Pasadena, an expensive yet necessary arrangement.
In July,
when the project is completed, production will shoot way up. The new turbines
will be capable of generating between 10 and 12 megawatts. Bearing in
mind that the campus requires up to 15 megawatts of power at the height
of the summer, the plants energy output will be closer to the target.
Over time,
several factors have raised Caltechs power requirements. The main
one is growth.
Although
the campus is small when compared to such behemoths as UCLA and MIT, it
has grown tremendously. Since 1967, when it was bounded on the north by
San Pasqual Avenue, the campus has increased in maintainable square feet
an astonishing 140 percent.
With this
growth came very technically complex and energy-intensive laboratories
and supporting facilities, including a new student residence, libraries,
and a gymnasium. Of course, they all need power to operate.
Bounded by
city streets, further campus expansion would seem to be inhibited. But
according to Ohadi, the campus has seen steady growth in power use of
about 3 percent per year over the last decade. He believes that the campus
will probably continue that trend.
The
buildings on campus will continue to grow and change, and we have to be
able to supply all of those buildings with all the things we need to run
a university, says Jesse McBurney-Rebol, a utility mechanic at Central
Plant. The big push right now, though, has been electricity. Its
the most important thing that were focusing on.
Another major
project in the planning stages will take advantage of the way that the
price of electricity varies during a 24-hour period. Power is more expensive
during peak daytime hours, and is cheaper at night. By constructing a
thermal-energy storage facility south of California Boulevard, Caltech
will be able to take advantage of off-peak hours to run its chillers and
produce large quantities of chilled water, which will be stored under
the north athletic field. During the day, the chillers will be turned
off, and the chilled water will be routed throughout campus, providing
relief from high daytime temperatures. The cost of construction is estimated
at about $6 million.
We
anticipate a payback in five years, Ohadi said of this second venture.
Thats when well make the money back, and after that
itll be free. Similarly, he projects that the cogeneration
project will reach the payback point in about three years. These are happy
words for the Institute, which recently floated a $70 million bond, some
of which will help finance energy projects.
Among the
existing and future projects is the installation of a microturbine at
the Administrative Technology Center that will provide power to Caltech
buildings north of Del Mar Boulevard. Others include the upgrading of
campus lighting, the installation of variable frequency drives on fans
and motors, and the repairing and upgrading of obsolete air-handling systems.
|